水泥墩光伏三角支架系统的安装过程
2023-05-11 10:30水泥墩光伏三角支架系统适用于户外或者平屋顶荷载量较大的情况。
The Cement Pier Tripod Solar Mounting Systems are suitable for outdoor or flat roofs with large loads.
一、结构示意图参考如下
The structural diagram is as follows:
A-水泥墩, 负重部件 作为底座基础,发挥负重和固定的作用
B-角钢 底梁 用于形成主支撑框架
C-角钢 背梁 用于形成主支撑框架
D-角钢 斜梁 用于形成主支撑框架
E-角钢 后斜撑 用于支撑横梁
F-C型钢 横梁 固定和支撑光伏组件板
G-角钢 拉杆 将横梁连接为整体
H-中侧压块 固定光伏组件板
A-Concrete pier Load, bearing parts As the foundation of the base, it plays the role of load-bearing and fixing
B-Angle Steel, Bottom beams which are used to form the main support frame
C-Angle Steel, Back Beams which are used to form the main support frame
D-Angle Steel, Inclined Beams which are used to form the main support frame
E-Angle Steel, Rear Brace which are used for supporting beams
F-C steel beam which are used to fix and support photovoltaic modules
G-Angle Steel, Tie Rod which are used to connects the beam as a whole
H-End Clamp and Middle Clamp, which are used to fix the photovoltaic module
二、部件组成如下:
The components are composed as follows:
三、安装步骤:
Installation steps:
1. 预制好负重水泥墩;
2. 在平屋顶上铺放水泥墩,间距按排布图纸布置。
1. Prefabricated load-bearing cement piers;
2. Lay cement piers on the flat roof, and the spacing shall be arranged according to the PV layout.
3.在水泥墩上安装角钢底梁;
4.使用外六角螺栓将角钢背梁、角钢斜梁相互连接与角钢底梁固定。
3. Install the Angle Steel Bottom Beam on the cement pier;
4. Use the hexagonal bolts to connect the angle steel back beam and the angle steel inclined beam and fix them with the angle steel bottom beam.
5. 依次将所有的支撑柱都安装好;
6. 安装横梁,使用外六角螺栓组合固定,并在横梁内加止动垫片;
7. 依次在三角支架上装好C型钢横梁;
5. Install all the structures in turn;
6. Install the crossbeam, fix it with a combination of hexagonal bolts, and add a stop washer inside the crossbeam;
7. Install the C-shaped steel beam on the triangular bracket in turn;
8. 在三角背梁上安装后斜撑,使其与横梁相连,使用外六角螺栓固定;与横梁连接时,加止动垫片。
8.Install the rear brace on the triangular back beam to connect it with the beam, and fix it with hex bolts; when connecting with the beam, add a stop washer.
9. 在每跨居中位置用角钢拉杆将两横梁连接,用六角螺栓、止动垫片固定。(跨距小于3000mm时,该跨不安装拉杆与后斜撑)
9.Connect the two beams with angle steel tie rods at the center of each span, and fix them with hexagonal bolts and stop washers.
(When the span is less than 3000mm, the span is not equipped with tie rods and rear diagonal braces)
10. 将长螺母插入横梁中,移动到适当位置,配合中侧压块将组件固定。(左:侧压块的安装;右:中压块的安装)
11. C型钢横梁需要加长时,采用横梁连接片连接,使用外六角螺栓、止动垫片固定。
10. Insert the long nut into the beam, move it to the appropriate position, and fix the component with the Mid & End Clamp.
(Left: installation of side pressure block; right: installation of middle pressure block)
11.When the C-shaped steel beam needs to be lengthened, it is connected with the Beam Splice, and fixed with the Hexagonal Bolt and the Stop Washer.
12. 依次将其余光伏组件固定好。
12.Fix the rest of the PV modules in turn.